Using IDEA StatiCa for designing an MRT viaduct

Singapore | Singapore | SMEC, KTP și Surbana Jurong Group
Acest articol este disponibil și în:
The MRT viaduct is an unique structure which integrates an MRT station with a bus interchange and adjoining commercial developments such as shopping malls. In this project, the MRT viaduct is fully integrated with the building structure on levels B2, B1, and L1 and features a landscaped roof that fits seamlessly within the viaduct. The design adheres to the latest Eurocode standards, with the inclusion of Singapore's national annex and references to PD6687-1 and PD6687-2. Using IDEA StatiCa, Ei Sheng Hong, the Bridge Design Lead at SMEC (part of the Surbana Jurong Group), along with his team, designed the superstructure, overcoming numerous challenges along the way.

About the project

This viaduct utilizes the innovative Floating Slab Track (FST) technology. It incorporates a double-pier system with full structural discontinuity to enhance noise and vibration control.

The superstructure includes two distinct types of LTA standard post-tensioned box girders, supported by unsymmetrical and unevenly loaded crossheads which are monolithically incorporated with the viaduct. Access openings are strategically located within these crossheads. The roof columns, designed to withstand derailment loads, uphold the UIC777-2R standards.

An extensive track-structure interaction analysis was conducted adhering to UIC774-3R guidelines, taking the use of FST into account. The design of the viaduct is intricately intertwined with its construction sequence, the roof structure above, and the building structure below. The viaduct's substructure is seamlessly connected to the building structure, with the pile cap forming an integral part of the B2 basement slab and the diaphragm wall of the West Wing structure.

inline image in article
Am folosit IDEA StatiCa Concrete pentru aproape toate proiectele noastre, pentru a rezolva probleme complexe și chiar simple, datorită a ceea ce oferă IDEA StatiCa. Apreciem calculele de proiectare concise pe care le poate genera.
Ei Sheng Hong
Ei Sheng Hong
Responsabil Proiectare Poduri – SMEC, KTP și Surbana Jurong Group
Malaysia

Engineering challenges

One project challenge was designing the concrete crossheads, which included a shared crosshead between two single box girders carrying rails for different directions. The crosshead's two openings altered the typical behavior, necessitating the design of asymmetrical structures that would have been difficult to calculate manually.

The viaduct's design includes a landscape roof with columns supported on the viaduct crosshead, which is supported centrally and laterally. Additionally, it's unevenly loaded with heavy weight on one side and none on the other.

inline image in article

Solutions and results 

Ei Sheng Hong's team successfully incorporated actual rebars into IDEA StatiCa Detail, generating valuable reports on their use. The software's automatic topology optimization calculated the strut-and-tie path, eliminating the need for time-consuming trial and error. 

The calculation process, including verification, took just a day, a significant reduction from the months it would take manually. This efficiency facilitated the swift completion of the design and production of reinforcement drawings.

inline image in article
IDEA StatiCa ne oferă instrumente ușor de utilizat, capabile să abordeze probleme complexe prin analize riguroase și rezultate clare.
Ei Sheng Hong
Ei Sheng Hong
Inginer Principal Proiectare Poduri –

Before IDEA StatiCa, the team had to make many assumptions and simplifications in their designs to capture the structural behavior. So, IDEA StatiCa Detail was exactly the software they needed to overcome these limitations. 

They were also impressed by the software's ability to perform simple analyses, offering the flexibility to extract necessary results and present them in a tabular format. This included various checks such as fatigue analysis. 

Furthermore, because they only needed to model everything once, it saved time. With just a click, the results were displayed. The robust design checks they produced eliminated the need for additional questions or explanations.

Dacă aș folosi un alt software, ar trebui să îl rulez de trei ori, deoarece există componente diferite. IDEA StatiCa este elegant și sofisticat, iar totul este cuprinzător.
Ei Sheng Hong
Ei Sheng Hong
Responsabil Proiectare Poduri – SMEC, KTP și Surbana Jurong Group
Malaysia

About SMEC

For more than 70 years, SMEC has built a reputation as a trusted partner on major transport and energy infrastructure projects around the world. Our design leaders and specialist teams draw on deep expertise and experience delivering projects across a range of diverse environments, from some of the world’s most remote locations to some of the densest urban surroundings.

Încercați IDEA StatiCa gratuit

Începeți perioada de probă astăzi și bucurați-vă de 14 zile de acces complet și servicii gratuite.

OTHER CASE STUDIES

Podul de Cale Ferată în Arc

Halle des Saveurs

SMEC, KTP și Surbana Jurong Group

SMEC, KTP și Surbana Jurong Group

Malaysia
De peste 70 de ani, SMEC și-a construit o reputație de partener de încredere în proiecte majore de infrastructură de transport și energie din întreaga lume. Liderii noștri de proiectare și echipele de specialiști se bazează pe o expertiză profundă și pe experiența dobândită în livrarea proiectelor în diverse medii, de la unele dintre cele mai îndepărtate locații din lume până la unele dintre cele mai dense zone urbane. Detalii